Finish schedule template: every surface in every room, in one table

A room-by-room finish schedule template covering floor, base, all four walls, ceiling, height, trim and doors, keyed to your specification codes. Free CSV, no email required.

By Idan Mann, founder of NYA

The short answer

A finish schedule tables every room against the finish specified for each surface — floor, base, each wall, ceiling, trim and doors — using codes that key to the specifications. It exists so a trade can see everything that applies to one space without reading the whole drawing set.

Download the CSVNo email, no account. Opens in Excel, Numbers or Google Sheets.

Drawings show where things are; schedules show what they are. A finish schedule is the table a painter, a tiler and a millworker each read one column of, and it is the reason a project can be priced without three phone calls per room.

Walls get four columns, not one. The moment a single room has a feature wall — and it will — a one-column schedule either lies or grows a paragraph in the remarks field that nobody reads.

What each column carries

Codes only. The code keys to the specification, which carries manufacturer, product, colour and installation requirements — one source, so a code can never mean two things.

ColumnWhat goes in itExample
Room #The plan number. Trades work from numbers; clients work from names. Carry both.102
Room nameAs named on the drawings and in the schedule, spelled identically in both.Primary Bath
FloorMaterial and finish code, plus setting pattern where it matters.PT-2, stack bond
BaseMaterial and height. The detail most often left off and most often queried on site.TB-1, 100mm
Wall NPer elevation, because feature walls are the rule rather than the exception.PT-1
Wall EPer elevation. Split walls are how a schedule stays true when only one of them is papered.P-3
Wall SPer elevation. Where three walls share a finish, repeating the code beats a remark saying “as N”.P-3
Wall WPer elevation. A blank here means unresolved, not “same as the others” — say what it is.P-3
CeilingFinish code. The ceiling *layout* — fixtures, vents, coffers — belongs on a reflected ceiling plan, not here.P-4
Ceiling heightAFF. Drives millwork, drapery and every fixture drop on the RCP.2700 AFF
TrimCasings, mouldings and their finish.P-5
DoorsDoor type and finish, keyed to the door schedule where you keep one.DR-2 / P-5
RemarksEverything the codes cannot carry — waterproofing extents, transitions, sequencing notes.Waterproof to 1.8m at shower

Keeping it honest

  • One source for the codes. A code that means two products in two documents is worse than no code at all.
  • Revision dates on the schedule itself. It changes more often than the drawings do, and an undated revision is how two trades end up working from different truths.
  • Discontinuations are traced through it. When a tile goes out of production, this table tells you every room it lands in before you write the change order.

The ceiling column here records the finish only. What is happening on that ceiling — fixtures, vents, changes in plane, switching — is a drawing, and our guide to reflected ceiling plans covers what belongs on one.

Common questions

What is the difference between a finish schedule and a specification?
The schedule says which finish goes where, by code. The specification says what that code is — manufacturer, product, colour, size, installation requirements. The schedule is for coordination; the spec is what you order from.
Does a finish schedule include furniture?
No. Furniture is FF&E and lives on its own schedule. The finish schedule covers the surfaces of the building — anything a trade applies rather than a truck delivers.

Or stop keeping it in a spreadsheet

This template works. What it cannot do is generate the proposal from the schedule, record the client's approval per item, or raise the purchase order from what they approved — which is the part that actually goes wrong. NYA is $49/mo for a solo designer and $129 for a studio of up to five, flat, with no per-seat billing.

Start freeDownload the CSV

More templates

  • TemplateFF&E schedule
  • TemplatePunch list
  • TemplateSpecification sheet

Keep reading

  • DefinitionFinish schedule
  • DefinitionMillwork
  • DefinitionShop drawing
  • GuideWhat Is a Reflected Ceiling Plan (RCP) — and When Do You Actually Need One?